SOAS into Senate House

Timeline

We are currently waiting for planning permission, the Timeline is subject to change when we have received this.

Spring and Autumn 2012

Consultation will take place with staff on how the space in the North Block will be used.  Further information about this will be available on this web site over the coming weeks.

May - August 2012

Professional team appointment process.

August 2012 - June 2013

Design process.

February - June 2013

Planning.

May - September 2013

Stage two tender.

Appointment of contractor.

December 2013 - July 2015

Construction programme.

July - September 2015

Handover and Commissioning.

September 2015

Opening.